The Rte 234/Brentsville Rd Interchange Needs Better Bike & Ped Access to and from Bus. Rte 234/Dumfries Rd

Routing for bicyclists and pedestrians in the approved Route 234/Brentsville Road Interchange Project design

In early February 2024, Active Prince William asked the Prince William County Department of Transportation to improve pedestrian and bicycle access and safety between the Business Route 234/Dumfries Road corridor in the vicinity of Godwin Drive and the Route 234/Brentsville Road Interchange project, which is nearing the end of its construction.  County staff replied that they will look into our request but did not commit to any action.  Our written request is copied below.


Potomac Local’s recent update on the Route 234/Brentsville Road Interchange project reported that this $55 million project is currently $2 million under budget.

We are inquiring about the County’s plans for safe and convenient pedestrian and bicycle access along the Business Route 234/Dumfries Road corridor between the new interchange and the City of Manassas.  From previous correspondence, Mr. Belita indicated a ten-foot wide shared use path will be built along the west side of Business Route 234/Dumfries Road between the Bradley Cemetery Way area and Godwin Drive.

We firmly believe that 10-foot wide shared use paths are needed along both sides of Business Route 234 to provide reasonable and much-needed pedestrian and bicycle access to and from this Interchange.

Along the west side of Business Route 234, the shared-use path between at least Godwin Drive and the Bradley Cemetery Way area will provide safe foot and bicycle access to and from Godwin Drive heading west (including to the adjacent Mayfield Trace community) and could also connect to a future northwestern extension of the regionally significant shared-use path along the Prince William Parkway leading from the Brentsville Road Interchange.  In addition, the nearest shared-use path within the City of Manassas is along the west side of Business Route 234, between Hastings Drive and Donner Drive.

Along the east side of Business Route 234, a shared-use path from the Bradley Cemetery Way area would provide optimal access to the shared-use paths being built within this Interchange project that a) head south to cross over Route 234 to reach both Brentsville Rd heading south and the existing regional path along southbound Route 234 and that b) meander east through the Interchange to reach Liberia Avenue Extended/Route 294 toward Manassas.

A shared-use path along the east side of Business Route 234 would optimally connect to the existing Bradley Square townhome development and the proposed Bradley South (REZ2003-00027) development.  From Bradley Manor Place, the existing Bradley Square subdivision streets readily lead to South Grant Avenue in the City of Manassas, a pleasant, existing low-traffic route for bicycling and walking that connects to Wellington Road (and from there to downtown Manassas via multiple routes).

We are disappointed that the current Bradley South rezoning proposal is rather inhospitable for bicycling and walking.  Business Route 234/Dumfries Road would have a 50 MPH design speed and a 45 MPH posted speed limit, and the developer of Bradley South would only be required to proffer a sidewalk along the east side of Dumfries Rd.  By contrast, the connecting segment of Dumfries Road at the south end of the City of Manassas has only a 35 MPH posted speed limit (which is better but also too high in our opinion).

Furthermore, with continued residential, commercial, and mixed-use development along the Business Route 234/Dumfries Road corridor (including the Prince William County Fairgrounds), just south of the Manassas City Limits, the density of development will be comparable to that planned along Centreville Road (Route 28) in Yorkshire.

We ask that the budget surplus from this project and proffers from the Bradley South rezoning be used to provide a 10-foot wide shared-use path along the east side of that roadway (Dumfries Rd), from the Bradley Cemetery Way area to at least Bradley Manor Place.

Beyond that, to the extent feasible, the Interchange Project budget should also provide much-needed pedestrian infrastructure for crossing Business Route 234/Dumfries Road at Godwin Drive, including high-visibility crosswalks, at least one raised pedestrian crossing refuge within the roadway median, and either a pedestrian-activated crossing beacon (e.g., HAWK signal) or a conventional traffic signal with full pedestrian crossing components for at least two of the existing intersection legs.

Please let us know how the Route 234/Brentsville Road Interchange Project will suitably accommodate active mobility to and from the already well populated Business Route 234/Dumfries Road corridor.

Without safe and convenient foot and bike connections to the new Interchange from Business Route 234, the new Interchange will degrade active mobility to and from that populated corridor, and the new active transportation infrastructure within the interchange will be very underutilized.  Waiting five or more years for possible future rezonings along Business Route 234/Dumfries Road is not acceptable to complete these critical sections.

If the surplus funds from the Interchange project cannot be tapped to build either another shared-use path or a signalized pedestrian crossing of Business Route 234/Dumfries Road at Godwin Drive, we believe that low-cost or no-cost alternative interim improvements could readily be implemented along the east side of Business Route 234/Dumfries Road that would still substantially improve pedestrian and bicycle access and safety between the Bradley Cemetery Way area and Bradley Manor Place.

Google Street View shows that–before the Interchange was constructed–the paved width of Business Route 234/Dumfries Road was already about four or five lanes wide (i..e., 48 to 60 feet of asphalt pavement) for most of the distance between Bradley Cemetery Way and Bradley Manor Place.  There appears to be only a short stretch between Godwin Drive and the south end of Bradley Square where the pavement narrows to about 36 feet, but only two lanes are presently needed for vehicular travel along that segment.

Thus, the restriping of that roadway segment (with or without any asphalt resurfacing) should allow for at least a continuous 10-foot or wider northbound paved shoulder area leading up to the long right-turn-only lane approaching Bradley Manor Place.  That shoulder area could be protected from roadway traffic with some sort of hard physical barrier to serve as an interim shared-use path along the east side of Business Route 234/Dumfries Road between the Bradley Cemetery Way area and Bradley Manor Place.

This recent photo (below) of northbound Route 234 Business/Dumfries Road near Bradley Cemetery Way shows that a wide paved shoulder is already present at that location.  While less wide than optimal, that existing paved shoulder could serve as an interim two-way shared-use path if it’s protected from the roadway traffic with a suitable hard barrier.

Northbound Business Route 234/Dumfries Road just north of the Interchange on February5, 2024

In addition, a striped conventional bike lane in each direction may also be feasible.  In the southbound direction, a striped on-road bike lane would be especially useful, from the Manassas City Line to Godwin Drive, for the dozens of bicyclists who participate in Bull Run Bicycles Tuesday Evening Shop Ride, almost every Tuesday evening during daylight saving time.  South of Godwin Drive, a southbound bike lane should not be needed because a new shared-use path will be located along that segment.

Finally, we again request that whatever pedestrian and bicycling improvements cannot be accomplished under the current Interchange project become required proffers as part of the Bradley South rezoning.

While Better, the Revised Design of the Route 234-Brentsville Road Interchange in Still Badly Flawed

Prince William County DOT’s currently proposed circuitous trail routing through the Interchange, assuming that a direct trail bridge connecting the existing Route 294 and Route 234 Trails is included in this project

Our proposed trail connections through the planned interchange to reach Route 234 Business (red line) and the future trail along the Route 234 Bypass (blue line).  A trail (red line) running along the north side of Route 234 would pass underneath both new roadway overpasses. The three light blue circles show where box culverts could allow the trail to be routed beneath highway ramps.  The areas shown in yellow are existing roadways that are planned to be removed.  This design eliminates all at-grade trail-roadway crossings, except to reach Route 234 Business.  However, by building a shared-use path along the west side of Route 234 Business (connecting to Godwin Dr), trail users would be required to cross only 5-lanes of stopped traffic at just the western leg of the signalized intersection of Bradley Cemetery Way and Route 234 Business, not 12-lanes of stopped traffic plus one lane of free-flowing right-turning traffic at two separate legs of that intersection.

This post follows up on the comments we previously submitted in response to the December 8, 2021 Design Public Hearing for Prince William County DOT’s Route 234-Brentsville Road Interchange Project.

On March 18, 2022, the County released this followup video presentation on the proposed project design.   County DOT staff are willing to at least partly addresses three concerns with the proposed trail connections that were raised at the Design Public Hearing:

1) In response to public comments from Active Prince William and others, the County is now studying the cost feasibility of a new, dedicated trail bridge over Rte 234, just east of the interchange, to directly connect the existing trails along Route 234 and Route 294.   If this trail bridge can be added without the project exceeding it’s $55 million budget, it will be included in this project.   Otherwise, it probably won’t.

2) In response to safety concerns raised by many about the four proposed closely spaced at-grade trail crossings of free-flowing highway ramps near Route 294 and Bradley Cemetery Way in the northeast corner of this project, those hazardous at-grade trail crossings may not be built, at least if the added trail bridge discussed above is actually built.    However, this change would produce a long, circuitous trail route between the western legs (Route 234 Bypass and Route 234 Business) and eastern legs (the existing trails along Routes 234 and 294) of this interchange (shown in the top image above).

3) In response to objections that the design completely omits the long-planned trail along the Route 234 Bypass that should join the existing trails along Route 234 and Route 294,  the design team has identified a future location for this trail along the northwestern edge of the interchange (see the blue line in the second image above).

However, all trail connections to and from Route 234 Business and the long-planned future trail along the Route 234 Bypass (aka Route 234 North) would still require a two-stage at-grade crossing of 12 signalized traffic lanes plus one free-flowing right-turn lane at the rebuilt intersection of Bradley Cemetery Way and Rte 234 Business plus a second at-grade trail crossing of a free-flowing highway ramp at the south side of the interchange (at the on-ramp from Brentsville Road) .  Those remaining design flaws would still create considerable delays and hazards for trail users.

Under Prince William DOT’s revised design for this interchange, this slow and hazardous crossing of 13 traffic lanes at two legs of the signalized intersection of Bradley Cemetery Way and Route 234 Business would remain.  All trail access and egress from either Route 234 Business or the future trail along the Route 234 Bypass would need to use this routing to join either of the existing trails along Route 234 and Route 294 or Brentsville Road.

As a followup proposal, we suggest routing the long-planned trail along the Route 234 Bypass along the north side of Route 234 (per the second image from the top), connecting that trail to both the existing Route 294 Trail to the east and to a new shared-use path along the west side of Route 234 Business (where the existing pavement, depicted in yellow, is planned for removal).   This trail (depicted with a red line in that image) would pass underneath both new roadway overpasses being built to carry Brentsville Road and Route 294 over Route 234 and could also pass underneath three single-lane interchange ramps inside box culverts (see the light blue circles).

Under our proposal, the long-planned trail along the Route 234 Bypass would run along the north side of Route 234 and pass under both planned roadway bridges.

 

Three short box culverts could be used to route our proposed trail along the north side of the Route 234 Bypass beneath three one-lane interchange ramps.  Only one such box culvert would be needed for the connection to Route 234 Business.

Our proposed design eliminates all at-grade trail-roadway crossings, except to reach Route 234 Business.  However, by building a shared-use path along the west side of Route 234 Business (connecting to Godwin Dr), where only a sidewalk is currently planned, trail users would be required to cross only 5-lanes of stopped traffic at just the western leg of the signalized intersection of Bradley Cemetery Way and Route 234 Business, not 12-lanes of stopped traffic plus one lane of free-flowing right-turning traffic at two separate legs of that intersection.

Our proposal could also lower the cost of this project by eliminating the need to include a 14-foot wide shared-use path on the proposed Brentsville Road bridge.

Active Prince William believes that first-class, safe and direct trail connections for all five legs of this interchange can and should be provided within this project’s existing budget of $55 million.

Our Final Comments on the Proposed Route 234-Brentsville Road Interchange Design

PWC’s Proposed Route 234-Brentsville Road Interchange (a grade-separated interchange with continuous green-T intersections).  To see the details, view the design display boards from the December 8 public hearing.

March 18, 2022 Update:  The County has posted this followup video presentation on the proposed project design, and a virtual followup public meeting is scheduled for March 22 at 6 pm.

Several of our concerns with this project are currently being addressed (although the trail bridge over Rte 234 just east of the interchange is merely being “studied” at present).

However, all trail connections to and from Rte 234 Business and the long-planned future trail along Route 234 North would still require a two-step at-grade crossing of 12 signalized traffic lanes at the rebuilt intersection of Bradley Cemetery Way and Rte 234 Business, and two of the original six at-grade trail crossings of free-flowing highway ramps would remain.  Those remaining design flaws would still create considerable delays and hazards for trail users.


Active Prince William submitted the following public comments to the Prince William County Department of Transportation in response to its December 8, 2021 Design Public Hearing on its proposed Interchange at Route 234 and Brentsville Road.  The public comment period closed on December 18, 2021.


The advertised design of the above-referenced project does not safely and effectively accommodate people bicycling, walking, or using other active transportation modes through the project area.  The design of the advertised non-motorized connections should be revised substantially to provide reasonable access and safety for people who are not traveling inside motor vehicles.

1) The Proposed Design Includes Too Many Dangerous At-Grade Trail Crossings of Free-Flowing, High-Speed Highway Ramps

This interchange is the connection point for Prince William County’s two major east-west cross-county shared-use paths; namely, the asphalt sidepaths along Route 294 (Prince William Parkway) and Route 234 South (Dumfries Road).  While the proposed design does include a circuitous shared-use path, meandering through the center of the interchange, that links both major paths, this advertised path connection would require people walking or bicycling to cross five separate at-grade crossings of high-speed highway ramps without any protection from traffic signals.  This tortuous path connection is not merely long, indirect, slow, and tedious; it is extremely hazardous and will both significantly deter trail use and lead to multiple pedestrian and bicycling injury crashes and eventually to traffic deaths.

Four of the six at-grade trail crossings of free-flowing, high-speed highway ramps that are included in the advertised design

Since this proposed interchange would create near-Interstate-highway-quality, free-flow connections for motor vehicles from all five approaches, it is unconscionable to have any at-grade trail-roadway crossings in this project. 

Rather than connect the two existing major trails via five at-grade highway ramp crossings within the center of the interchange, bicyclists and pedestrians should instead be routed near the eastern and northern perimeters of this interchange via pedestrian/bicycle overpasses of three legs of this intersection; namely, Route 234 South, Route 294, and Route 234 Business.   While all three pedestrian/bicycle overpasses proposed below are clearly warranted for safe and equitable access, they are listed above in priority order.

With that said, the trail approaches to many of the proposed at-grade roadway crossings in the present design are often very short and nearly parallel to the crossed roadway, especially at most of the four at-grade roadway crossings near the intersection of Bradley Cemetery Way and Route 294.  With such closely spaced crosswalks and sharply bent trail approaches, a bicycle rider would need to fully stop well before reaching the crosswalk, dismount, and manually reposition her bicycle to clearly view the approaching cross-traffic, and she will thus require much larger gaps in traffic to safely cross each roadway ramp.  The clustering of some of these crosswalks and the resulting short path segments between them would also likely create conflicts and collisions with any trail users approaching from the opposite direction.  If the final design retains any at-grade roadway crossings, the trail approaches should be as perpendicular to each crossed roadway (or in direct line with each crosswalk) as possible and substantially longer than the crosswalk itself.

The advertised design includes four closely spaced at-grade path crossings of free-flowing highway ramps near Route 294

The proposed shared-use path junction for the sidepath along Brentsville Road, near the southern end of the intersection, is also poorly designed.  The approach of the Brentsville Road sidepath to the Ramp C crossing is far too close and nearly parallel, not perpendicular, to Ramp C.  In addition, the Brentsville Road sidepath joins the longer path leading to Route 234 South at a sharp 90-degree angle, rather than making gentle Y-shaped connections much farther east of Ramp C.  The latter design flaw is replicated at the path junction near Bradley Cemetery Way and Route 234 Business.  Published AASHTO and VDOT guidance describe how to design appropriate path connections for people riding bicycles at 15 to 20 MPH.

The sidepath along Brentsville Road is poorly designed at its northern end near the Ramp C crossing.

 

2) Separating Shared-Use Paths from High-Speed, Free-Flowing Vehicle Traffic is a Long-Standing Practice in Northern Virginia

The practice of designing and building high-quality shared-use paths along and/or across limited-access highways without any at-grade road crossings has at least a 40-year history in Northern Virginia.  When the Virginia Department of Transportation designed and built I-66 in Arlington circa 1980, it established a continuous 10-foot asphalt path immediately adjacent to that highway with zero at-grade roadway crossings for the more than four miles between N Scott St in Rosslyn and the City of Falls Church at N Van Buren St and Route 29.

The 45-mile Washington & Old Dominion (W&OD) Trail, which runs from Shirlington to Purcellville, is Northern Virginia’s preeminent active transportation and recreation facility, largely because it has zero at-grade crossings of fast or busy roadways that are not protected with traffic signals.

In Arlington, the W&OD Trail benefits from both local roadway overpasses of the adjacent I-66 to cross under N. Ohio St and N. Patrick Henry Dr and stream underpasses for the adjacent Four Mile Run to cross under N. Sycamore St, N. Wilson Blvd, N. Carlin Springs Rd, and Arlington Blvd.  As a result, the W&OD Trail has zero at-grade roadway crossings for the nearly four miles between Columbia Pike and the Falls Church line at N Van Buren St.

For at least the past 30 years, NOVA Parks (formerly NVRPA) has required all builders of new or widened roads across its W&OD Trail to include a grade-separated crossing for the trail.  As a result, the W&OD Trail west of Four Mile Run now includes more than two dozen separate trail overpasses or underpasses at Route 29 in East Falls Church, Route 7 in Falls Church, I-495, American Dream Way, Reston Parkway, Town Center Parkway, Fairfax County Parkway, Herndon Parkway East, Center St in Herndon, Herndon Parkway West, Church Road, Atlantic Blvd, Route 28/Sully Road, Pacific Blvd, Loudoun County Parkway, Ashburn Village Blvd, Claiborne Parkway, Belmont Ridge Road, Battlefield Parkway SE, Route 15, Plaza St SE, Route 7/Harry Bryd Hwy, the Route 9/Route 7 Interchange, and the Route 287/Route 7 Interchange.  Many of those grade-separated roadways have lower traffic speeds and/or volumes than Routes 234 and 294.

Currently, the I-66 Outside the Beltway Express Lanes Project is in the process of building 11 miles of shared-use paths adjacent to I-66 in Fairfax County, as well as safe bicycle and pedestrian facilities on nearly all of the roads that cross I-66.  These new bicycle and pedestrian connections have been carefully and creatively designed to avoid at-grade roadway crossings, especially crossings with free-flowing, high-speed traffic.

Operated by the National Park Service’s George Washington Memorial Parkway unit, the 18-mile Mount Vernon Trail between Rosslyn and the Mount Vernon Estate is another premier shared-use path in Northern Virgina.  Because it follows the Potomac River, the Mount Vernon Trail has always had few at-grade road crossings.  Nevertheless, many millions of dollars have been invested over the years to remove busy at-grade highway ramp crossings near Reagan National Airport, and—with no highway ramp interruptions—to connect the Mount Vernon Trail to Rosslyn, the Pentagon, and Crystal City and to cross the Potomac River on the Woodrow Wilson Bridge.

In recent years, the Virginia Department of Transportation has been building a network of pedestrian and bicycle overpasses of I-495 and the Dulles Toll Road in the Tysons area, including along Route 7 across the Dulles Toll Road, Trap Road over the Dulles Toll Road in Vienna,  the Jones Branch Connector over I-495 south of the Dulles Toll Road in McLean, and the Tysons One/Old Meadow Road overpass of I-495 near Pimmit Hills.

Bicycling and walking are viable transportation and very popular recreation modes in communities with high-qualify shared use paths, and the absence of at-grade highway ramp crossings is a key contributor to the safety, use, and enjoyment of those paths.  Prince William County will never create the types of high-quality paved trails enjoyed in most other Northern Virginia localities if it continues to build shared-use paths with hazardous at-grade crossings of highway ramps.

 

3) Install a Pedestrian/Bicycle Bridge over Route 234 on the East/South Side of the Interchange to Create a Safe and Direct Connection between the Route 234 and Route 294 Paths

The Route 234 and Route 294 sidepaths–the two major existing bike/ped facilities within the project area—could be linked very safely and directly by building a pedestrian/bicycle bridge between these two trails on the east/south side of the interchange in the vicinity of the Meadows Farms Garden Center.  Because the elevation on the south side of Route 234 is considerably higher than the roadway, no long bridge approach should be needed on that side of the overpass.

Our proposed direct connection of the existing Route 294 and Route 234 shared-use paths via a pedestrian/bicycle overpass of Route 234 on the east side of the interchange near the Meadows Farms Garden Center

 

4) Incorporate Safe and Direct Connections to and from Route 234 Business (Dumfries Road) and the Planned Trail along Route 234 North

Even if the direct pedestrian/bicycle bridge requested above is built, safe and efficient bicycling and walking connections would still be needed to and from all five legs of this interchange; namely Route 294 (Prince William Parkway), Route 234 South (Dumfries Road), Route 234 North (Prince William Parkway), Brentsville Road (Route 649), and Route 234 Business (Dumfries Road).

Although the current Prince William County Comprehensive Plan calls for building a major shared-use path along Route 234 North, the current project design does not depict this future trail or its connections to the four other legs of this interchange.  The current design should be modified to identify the right-of-way and connections for the future Route 234 North shared-use path within the project limits.

Presently, Route 234 Business (Dumfries Road) provides bicycle and pedestrian access to the project area from most of the City of Manassas, the Bradley Square development, and the Godwin Drive corridor.  Bicyclists and pedestrians now readily use Route 234 Business to access Brentsville Rd, the Route 234 South sidepath, and the Route 294 sidepath via the roadways and crosswalks at the two nearby existing Route 234 intersections (and alternatively via Bradley Cemetery Way if desired).

The proposed design, however, would severely degrade this walking and bicycling access to and from Route 234 Business by expanding the limited-access control perimeter and by creating a large new signalized intersection at Route 234 Business and Bradley Cemetery Way.  To access any other leg of the interchange, bicyclists and pedestrians from Route 234 Business (and also the future shared-use path along Route 234 North) would apparently need to 1) cross two separate legs of a large, signalized Route 234 Business/Bradley Cemetery Way intersection—spanning a total of 12 vehicle lanes—2) cross a free-flowing lane of right-turning traffic from northbound Brentsville Road, and 3) finally cross either one or four-additional high-speed highway ramps within the center of the interchange, depending upon one’s destination.  This proposed pedestrian and bicycle access is neither safe nor effective and is a significant degradation of the existing conditions.

The advertised design would require at least a four-stage maneuver for pedestrians and bicyclists using Route 234 Business (or the future shared-use path along Route 234 North) to access any other leg of this interchange: 1) cross five lanes of stopped traffic at Route 234 Business, 2) cross seven lanes of stopped traffic at Bradley Cemetery Way, 3) cross one-lane of free-flowing right-turning traffic from northbound Brentsville Road, and 4) cross either one or four additional highway ramps—located elsewhere inside the interchange–with free-flowing, high-speed traffic, depending upon one’s final destination.

The current design should be modified to add an elevated trail on a berm along the north side of Bradley Cemetery Way, with pedestrian/bicycle bridges over both Route 234 Business and Route 294.  Such an elevated trail would connect the existing Route 294 path with the west side of Route 234 Business and the long-planned future trail along Route 234 North.  Placing this trail connection on a berm along the north side of Bradley Cemetery Way should lower construction costs and improve walking and bicycling conditions by minimizing grade changes along this trail connector between the pedestrian bridges over Route 294 and Route 234 Business.  Integrating these safe and direct grade-separated trail connections as part of the current project should provide them at far lower cost than if constructed later as one or more standalone projects.

Rough alignment of our proposed grade-separated trail connections along the northern perimeter of the interchange, with two relatively short pedestrian/bicycle overpasses of Route 234 Business on the west (connected to future shared-use paths along Route 234 Business and Route 234 North) and Route 294 on the east (connected to the existing Route 294 shared-use path).  Between Route 234 Business and Route 294, the connecting path could be built on a berm along the north side of Bradley Cemetery Way.

 

5) Reduce Interchange Construction Costs by Eliminating Unnecessary Trail and Roadway Features

To offset the cost of adding up to three pedestrian/bicycle bridges, the current design could be modified to eliminate unnecessary features.

If all three pedestrian/bicycle bridges recommended above are built over the eastern and northern edges of this interchange, all currently designed pedestrian/bicycle infrastructure within the center of this interchange would be unnecessary and could be eliminated, including the currently proposed 14-foot-wide shared-use path on the western interchange bridge.

The cost of the western interchange bridge should be further reduced by eliminating the advertised continuous green-T intersection at the exit ramp from southbound Route 234 and by eliminating one of the two northbound travel lanes from Brentsville Road on the western interchange bridge.  Traffic volumes on Brentsville Road, which had an AADT of only 2800 in 2019, will never warrant two northbound lanes through this interchange.  Eliminating one unnecessary travel lane (and potentially also the shared-use path) would reduce the cost of this roadway bridge considerably.  A traffic signal, stop sign, or a roundabout could replace the proposed continuous green-T intersection.

 

To reduce project costs, one northbound lane from Brentsville Road could be eliminated on the western overpass.  This second northbound lane is not warranted by current or future Brentsville Road traffic volumes and was only designed to accommodate an unnecessary continuous green-T intersection for traffic exiting southbound Route 234.  If the advertised design is modified to add all three pedestrian/bicycle overpasses recommended above, the 14-foot wide shared-use path could also be eliminated from this overpass.  The width of the advertised western overpass could thus be reduced 39%, from 67 feet to 41 feet.

Reducing northbound Brentsville Road to a single lane though the interchange would also reduce the widths of the roadway north of the western overpass and the width of the signalized intersection of Brentsville Rd/Route 234 Business at Bradley Cemetery Way.

The Route 234 Business/Dumfries Road roadway is already needlessly wide south of Godwin Drive.  According to VDOT’s 2019 traffic count data, this roadway segment has an AADT of only 8600.  Presently, the Route 234 Business roadway south of Godwin Drive is five lanes wide, whereas only three lanes of roadway (one travel lane per direction plus space for a left-turn lane in the center) would adequately accommodate a future doubling of this Route 234 Business Traffic (i.e., to an AADT of 17,200).

Rebuilding Route 234 Business between Godwin Drive and Bradley Cemetery Way as a three-lane roadway, instead of as a five-lane roadway, would allow the addition of both a shared-use path and a sidewalk within the existing right-of-way along this key road segment.  Moreover, the shared-use path (and not the sidewalk) should be located along the west side of Route 234 Business to align with the west-side path just built within the City of Manassas between Hastings Drive and Donner Drive.

Thank you for considering these comments.  We look forward to seeing a substantially modified final design for the shared-use path connections that will eliminate all at-grade roadway crossings and accommodate safe and reasonably direct pedestrian and bicycle access to and from all five legs of this key interchange.


On December 27, 2021, we submitted the following additional comment:

Building 12-foot-wide travel and turn lanes on Brentsville Road, Route 234 Business, and Bradley Cemetery Way is clearly excessive, since 11-foot-wide lanes are more than adequate for those local, lower-speed roadways.  Designing 11-foot travel lanes on the Brentsville Road bridge over Route 234 would further lower the cost of building that overpass.  With 8-foot-wide paved shoulders included on that overpass, 12-foot-wide travel lanes are most definitely wider than needed.

A narrower Route 234 Business on the north side of Bradley Cemetery Way would also reduce the cost of a pedestrian and bicycle overpass at that location and would shorten pedestrian crossing times if at-grade crosswalks are still included at Route 234 Business and/or Bradley Cemetery Way in the final design.

###

Active Prince William’s Initial Comments on the Proposed Design of the Route 234-Brentsville Road Interchange

 
PROBLEM:
Forcing bicycle and pedestrian users to cross FOUR separate free-flowing, high-speed vehicle lanes is an unacceptable way to connect two of the major trails in the county.  The section should be removed from the design.  It is too dangerous.  [Added Note: The proposed design forces bicyclists and pedestrians to negotiate a fifth high-speed at-grade road crossing (of the ramp from northbound Brentsville Road to southbound Route 234) to actually link these two major trails.  Furthermore, to access or egress Route 234 Business/Dumfries Rd, bicyclists and pedestrians would be forced to negotiate a sixth high-speed at-grade road crossing plus 12 vehicle lanes at two controlled intersection legs at Bradley Cemetery Way.]

 

RECOMMENDED SOLUTION:
Add an additional bike/ped bridge crossing of Route 234 south/east of the planned interchange to directly and safely connect the Route 234 Trail and the Prince William Parkway Trail.

 

HOW TO PAY FOR THIS RECOMMENDED SOLUTION:
1) Remove the proposed bike/ped infrastructure with four at-grade roadway crossings from the Bradley Cemetery Way area:

2) Change the Continuous Green-T Intersection at Brentsville Road and the off-ramp from VA234 Bypass South to a Roundabout, Standard Two-Phase Traffic Light or a Three-Way Stop Sign.  Future traffic volumes do not warrant the expensive infrastructure needed for a Continuous Green-T Intersection.

3)  Remove one northbound lane from the planned Brentsville Road Bridge to create a smaller/cheaper bridge footprint.  Future traffic volumes do not warrant having two northbound vehicle lanes on this bridge.

Design Public Hearing for PWC’s Route 234-Brentsville Road Interchange Project, December 8, 2021 at 6:00 PM

Prince William County’s proposed Route 234-Brentsville Road Interchange includes four treacherous at-grade shared-use path crossings of free-flowing high-speed roadways to link the Prince William Parkway and Route 234 sidepaths.   As an alternative to this dangerous and circuitous trail routing, Active Prince William advocates a simple trail overpass on the east/south side of this interchange to safely and directly link Prince William County’s two major trails.

 

From the Office of Coles District Supervisor Vesli Vega:

A public hearing on the proposed Brentsville Interchange Project will be held on Wednesday, December 8th at 6pm at the Lake Jackson Volunteer Fire Department, 11310 Coles Drive in Manassas.

The meeting can also be viewed live online at https://www.pwcva.gov/department/transportation/current-road-projects.  The Project team will make a short presentation beginning at 6:30 p.m. and answer questions for the duration of the meeting.

The purpose of the public hearing is to receive public comments on the design of the Route 234 Brentsville Road Interchange Project and associated Limited Access Control Changes in the Coles Magisterial District.  This Project will involve a change and break in Limited Access Control.

Preview the Project information and Design Public Hearing plans including the environmental documentation on the Prince William County Department of Transportation website at https://www.pwcva.gov/department/transportation/current-road-projects.  [Note: The five linked documents related to the current design are listed at the bottom, with links depicted in green.  The blue links are for the obsolete March 2020 design].

The deadline to submit comments is December 18, 2021.  The public may provide written or verbal comments at the Design Public Hearings, mail them to Ms. Mary Ankers, P.E., Project Manager, at the Prince William County Department of Transportation, 5 County Complex, Suite 290, Prince William, VA 22192, or email them to [email protected].   Please reference “Route 234 Brentsville Road Interchange Project PH Comments” in the subject heading.

Please find the Project Schedule Below: